A Word from Our Owners – St. Joan of Arc Church
-
Category
Studio-Community, Perspectives -
Posted By
Schmidt Associates -
Posted On
Aug 20, 2019
Molly Ellsworth has been the Parish Business Manager at St. Joan of Arc Catholic Church for eight years and served various churches in Indianapolis; Charleston, SC; and Chicago for 25 years. She earned both undergraduate (B.A. History) and graduate degrees (Master of Leadership Development) from St. Mary-of-the-Woods College.
Schmidt Associates worked with St. Joan of Arc Church on a phased renovation project, which included mechanical system upgrades, accessibility improvements, and interior restorations.
What was the goal of the restoration and improvements to St. Joan of Arc?
Our goal was to repair, refurbish, reinforce, and restore. This included a new HVAC system, electrical work, ADA (Americans with Disabilities Act) accommodations, lighting, floors, and restoration of the interior.
We didn’t have air conditioning. In the summer, it was very hot in the church until about November, and then it got cold. Our building would cycle like that continuously and had done so for 85 years. It was becoming too much for the church; you could see the deterioration of the interior. It looked like an ancient Roman church, and not in a good way.
Why did you decide to take a phased approach to these projects?
Our 100th anniversary is in 2021, so we wanted to have all of our projects finished by then. We started with the end in mind and worked backwards, initiating the project in 2012.
One of the reasons we used a phased approach was fundraising. We did a five-year fundraising pledge, so we could use the cash from the pledges we were getting before the rest came in. This would allow us to start projects and see results, which would in turn beget more fundraising. We knew in terms of cash flow and archdiocesan fundraising guidelines, this would be easiest for us. We could manage it without taking out a loan.
With this approach, if you end up receiving more funding than you anticipated, just like with a home improvement, you can then get higher-end fixtures than you anticipated or complete additional projects. If you don’t get all of the funding, hopefully you planned accordingly and prioritized the most important projects. As cash comes in later, you can pick back up.
Why was planning so far in advance important?
By giving ourselves so much time, we were really able to delve into all the systems and focus in on things that had to get done, things that would be nice to get done, and things that would be an added bonus to get done. That helped shift our brains into “phase mode,” so we were able to easily embrace each phase and do it right and do it well. This meant we were not having to go back and do change orders all the time.
How did you sell the projects to parishioners?
St. Joan of Arc Church is beloved on the northside. It’s hard to find someone on the northside who isn’t touched by this church in some fashion. Whether it’s once a year at French Market, or they attended a wedding here, or they got married here, or their parents or grandparents or great grandparents got married here. Having been here for almost 100 years, we’ve touched generations of lives.
It was an easy message. We didn’t initially say we were going to do it in a phased approach, but we did say we would begin once we had enough cash to start the projects. They understood that as soon as we got $1.5 million, we could get air conditioning. When you ask 700 families for air conditioning money in the summer, hopefully you get more than you need! Then the excess from air conditioning can go toward new paint or organ restoration.
How have the phased improvements been received?
AC was huge. It used to get so hot in the summer that people would go to other parishes. Last summer, after putting in the new HVAC, we saw a much higher percentage of people stay in the pews over the summer. That was a great win for us.
What they’re all really excited about at this point is the floor. The floor was 90 years old and was falling apart; it was designed to last maybe 20 years. The original design was for a terrazzo floor, and the parish ran out of money when they were building it. We have the opportunity now to finish what the architect and designers had originally intended. Folks are excited to see how it was meant to be.
We moved out of the church at end of May to finish the improvements. Few people have been inside since then. We’ve had some photographers who have been in and are posting on social media, and the response has been huge for us. People are very excited to get back in the church; they’re seeing the pictures, and it’s gorgeous. To see everyone’s excitement building is fantastic.